Water & Environment · Oman
Desalination Plant Efficiency Upgrade
Energy-recovery and control upgrades for a 20,000 m³/day reverse-osmosis plant.
- Year
- 2024
- Duration
- 12 months
- Status
- Completed
- Our role
- Engineering & integration
-17%energy per m³
20,000 m³daily capacity maintained
4RO trains upgraded
The challenge
Energy costs were rising and the plant’s controls were near end of life, but the utility could not take the plant offline during peak summer demand.
Our approach
SEYA Projects engineered the energy-recovery retrofit and staged the works train by train. SEYA Tech migrated the control system and secured remote access for the operator.
Scope of work
- Energy audit
- Retrofit engineering
- Staged installation
- Control-system migration
- OT security
Timeline
- Audit & designQ4 2023
- Train-by-train worksQ1–Q3 2024
- OptimisationQ4 2024