Apron & Remote-Stand Expansion
Nine new remote stands with ground lighting, visual docking guidance and airside security systems — delivered while the airport stayed fully operational.
- Year
- 2024
- Duration
- 18 months
- Status
- Completed
- Our role
- Construction management & systems integration
9new code-C/E stands
0operational disruptions
1,140night shifts managed
The challenge
Works had to be carried out on a live airside, with night-only windows near active taxiways and zero tolerance for disruption to scheduled operations.
Our approach
SEYA Projects managed phasing, contractor coordination and airside permits, and integrated lighting and docking guidance into the airport’s control systems. SEYA Security & Intelligence designed the CCTV and access-control extension for the new stands.
Scope of work
- Construction management
- Airside phasing & permits
- AGL & VDGS integration
- Airside CCTV & access control
- Testing & commissioning
Timeline
- Design & phasing planQ1 2023
- Enabling worksQ2 2023
- Main works (night windows)Q3 2023 – Q2 2024
- CommissioningQ2 2024