Grid Substation & Transmission Connection
All projects

Energy & Utilities · Central Java, Indonesia

Grid Substation & Transmission Connection

A 150/20 kV substation and 18 km transmission line connecting a new renewable plant to the national grid.

Year
2025
Duration
22 months
Status
In progress
Our role
Owner’s engineer
150/20 kVsubstation
18 kmtransmission line
On-timegrid energisation

The challenge

The plant could not monetise generation until a compliant grid connection and substation were energised, under the utility’s technical and permitting requirements.

Our approach

SEYA Projects reviewed the connection design, managed the EPC contractor, witnessed factory and site acceptance tests and coordinated energisation with the utility.

Scope of work

  • Connection design review
  • EPC management
  • Right-of-way & permitting
  • Protection & SCADA
  • Factory & site acceptance tests
  • Energisation

Timeline

  1. Design & permits2024
  2. ConstructionQ1–Q4 2025
  3. Testing & energisationQ1 2026